Top Summary Section
Total Projects: 7
Total Tasks: 37
Tasks Completed: 37 (100% completion rate as of 11-03-23).
Left Panel: Projects Completion
A horizontal bar chart shows the percentage completion of individual projects:
VIOLET Project: 11% complete
BROWN Project: 34% complete
SILVER Project: 61% complete
PINK Project: 86% complete
BLUE Project: 100% complete
ORANGE Project: 98% complete
RED Project: 100% complete
Middle Panel: Task Progress
1/Overdue Tasks
Lists tasks that are overdue, along with details like project name, task, assignee, end date, progress, and the number of overdue days. For example:
Task ORANGE 9 (Danny): 90% complete, overdue by 7 days.
Task VIOLET 1 (Morgan): 30% complete, overdue by 3 days.
2/Average Task Progress
A donut chart shows that tasks are, on average, 69% complete.
3/Tasks Status
A pie chart categorizes tasks by status:
Completed: 18 tasks
In Progress: 12 tasks
Not Started: 7 tasks
Right Panel: Resource Usage
A bar chart displays resource allocation by team member:
Whitney: 56 units
Jordan: 56 units
Bob: 40 units
Sarah: 33 units
Mike: 27 units
Danny: 17 units
Morgan: 14 units
Key Insights
Projects like BLUE and RED are fully completed, while others like VIOLET and BROWN are lagging significantly.
Despite overall task completion, some tasks are overdue, with notable delays in the ORANGE and VIOLET projects.
Resource usage is uneven, with Whitney and Jordan handling more workload compared to others like Morgan and Danny