The dashboard presents an analysis of NOK (Not OK) Critical & Major Checklist Items impacting network reliability and safety across different regions, sites, and activity types.
Total Work Orders (WO): 648
Total Sites: 512
Total EM CL Items: 27.8K
Covered Regions: 7
Key Findings ? High Impact Issues (Top NOK Items)
The most frequent critical issues identified:
Power Main / Major alarms (342 cases)
Door alarms (316 cases)
Breaker condition & wiring (312 cases)
AC temperature settings (288 cases)