A university student housing development project at Tanta University, comprising comprehensive construction and infrastructure works. The project scope includes site preparation, piling and foundation works, structural construction, architectural finishing, electrical and mechanical installations, fire protection systems, elevators, external works, and final testing and commissioning.

The project schedule was developed and analyzed using Primavera P6, comprising 974 activities and 1,364 relationships, with a planned project duration from January 2020 to March 2027. The programme covers the full project lifecycle, from initial site handover through construction, systems commissioning, and preliminary handover.