A construction project comprising multiple building sections (Parts A1, A2, A3, and A4), including foundation works, structural steel installation, slab and beam construction, blockwork, façade finishing, and project handover.

The project schedule consists of 624 activities and 1,047 relationships, covering the full project lifecycle from mobilization and site preparation through construction, testing, commissioning, and final handover. The programme was developed and monitored using Primavera P6, with a planned project duration from July 2025 to June 2026.