· Tendering & Initiation Phase; reviewed different tender packages and developed tender schedules such as
construction projects and landscape projects.
· Planning & Development Phase; developed and maintained detailed baseline for approval for
VYE-SODIC New Zayed.
· Monitoring & Controlling Phase; updating, reporting, monitoring and controlling all assigned projects such as
THE ESTATES-SODIC New Zayed & VILLETTE-SODIC New Cairo.
· Preparing different progress reports such as daily, weekly and monthly reports including dashboards.
· Monitor site work and communicate with construction team, highlight critical activities, look ahead activities,
delayed activities and suggest corrective actions.
· Attend Weekly and Monthly Client meetings to discuss project actual progress with respect to Earned Value
Management.
· Track and Identify the Cause/Claim Triggers; review any site instructions or scope changes which may affect
project contractual dates.2
· Participated in carrying out Delay Analysis study through TIA methodology, meanwhile studied different
Delay Analysis techniques preparing for an extension of time (EOT) Claim.
· Prepared a Revised Schedule for THE ESTATES-SODIC New Zayed after approval of a specific extension of
time (EOT).
· Prepared different Payments for Sub-Contractors.