GENERAL NOTES
1- All levels are in meters, all dimensions are in
millimeters.
2- All blockwork exceeding 4 m height to be reinforced
horizontally.
3- All opening heights and sill heights are measured from
F.F.L .
4- Plastering should be stop 100mm above false ceiling.
5- Façade, plans, toilets, stairs, elevators, escalators,
doors, windows, internal elevations, screed, and handrails
drawings will be submitted separately
6- Builder work and wall openings to be according MEP
requirements.
7- Solid cement masonry bricks for assemblies below
grade, wet areas, first three courses of walls and
boundary of opening, back of mechanically fixed stone
cladding and at opening jambs.
8- 3 courses of solid cement masonry bricks under
bearing plates, beams, lintels and similar conditions
unless otherwise indicated.
9- For wall types and fire rating refer to the wall types
tags ( M: minutes, HR: hours ).
10- The underside of concrete floor slabs or beams and
the top joint shall be filled with fire stopping material
( as approved material ).
10- Control joints does not exceed 15 meters.
11- The filler at the exposed faces of expansion joints
shall be cut back 20mm or on completion of the
structure and the joint sealed with a joint sealant.
12- Mechanical equipments and pits to be referred in
structural and mechanical shopdrawing